Design-assist for the newly constructed 36.4-megawatt hydroelectricity power plant in Pella, IA retrofitted to the existing dam reservoir. This project was an excellent example of how the design-assist process can save a project money. As part of this design-assist process, our team reviewed the one-lines and general arrangements provided by the engineer and was able to reduce the feet of cable used by 53,000+ as well as the number of raceways used by 13,500+. This resulted in over 6,000+ hours of saving to the Client.